A cycle time calculator works out how long a process takes per unit, the takt time that demand requires, and the link between work in process, throughput and lead time. Use it to check whether a line can keep up with demand and to see how much work is waiting inside a process.
How to use the cycle time calculator
- Choose what you want.
- Enter the time and units, the available time and demand, or two of L, λ and W.
- Press Calculate.
Cycle time
Cycle time is the time required to produce a part or complete a process, as timed by actual measurement [1]. For a production process that makes units one after another, it is the production time divided by the number of units made, which is our own working, because the page gives no formula. Making 240 units in 480 minutes is a cycle time of 2 minutes per unit, a rate of 0.5 units per minute. The rate is the inverse of the cycle time only for a single sequential process, with no parallel stations.
Takt time
Takt time is the available production time divided by the customer demand, T = Ta ÷ D [2]. Ta excludes breaks and expected stoppages, which is our own note. The source's example is a factory that runs 480 minutes a day against a demand of 240 widgets a day, which gives a takt time of two minutes [2]. Another example of ours is a shift of 480 minutes less two breaks of 30 minutes and two stops of 10 minutes, which leaves 400 minutes, with a demand of 400 units a day, and that gives one part per minute.
Comparing the two
The takt time is the pace that the customer sets, and the cycle time is the pace that the process can deliver. If the cycle time is at most the takt time, the process can keep up with demand. If it is longer, it falls short. The calculator compares them when you enter both, and gives the margin as a percentage. When a process cannot produce at takt, it needs more resources, a faster method or lower demand, which is our own view.
Little's law
Little's law says that L = λW, where L is the average number of items in the system, λ the average arrival rate and W the average time an item spends in the system [3]. It deals with long-term averages [3]. For example, 10 customers an hour with an average stay of half an hour give 5 customers in the system. Rearranged, W = L ÷ λ, so 2 customers in a system fed at 10 an hour stay 0.2 hours on average. These two examples are our own arithmetic.
Work in process
The paper ties the law to operations management, where it links throughput, the number of items in the system and the time they spend there [3]. Mapping it to a factory, L is the work in process, λ the throughput and W the lead time, a mapping of our own. If a line has 50 units in process and finishes 10 an hour, a unit spends 5 hours in the system. Reducing the work in process shortens the lead time, with the same throughput.
A worked example
A shop makes 240 units in an 8-hour shift of 480 minutes. Its cycle time is 2 minutes. The demand is 200 units, and 400 minutes are available, so the takt time is also 2 minutes, and the process just keeps up. If the demand rises to 250 units, the takt time falls to 1.6 minutes, and the 2-minute cycle time is 25 percent too slow. These figures are our own arithmetic.
Choosing the time unit
The calculator does not convert units. Enter all times in the same unit, such as minutes or hours, and the results come out in that unit. For Little's law the rate must be per the same unit as the time. For example, 10 per hour goes with a time of 0.5 hours.
Limits
The simple formulas assume a steady state. If demand or production varies a lot, the averages hide the swings. A process with several stations is held back by the slowest, so its cycle time is that of the bottleneck. Use the calculator for a first check, and look at each station to find the real constraint.
Improving the numbers
To cut cycle time, find the slowest step and either speed it up, add a second station or split its work. To meet a shorter takt time, the process needs a cycle time at or below the new value. To shorten lead time, reduce the work in process, which Little's law shows is the most direct lever when throughput is fixed.
Quick reference
For one station, the output per hour is 60 divided by the cycle time in minutes. A cycle time of 2 minutes gives 30 units an hour. For stations in a line, the slowest one sets the pace of the whole line.
Common mistakes
- Confusing takt and cycle time. Takt is set by demand, cycle time by the process.
- Including breaks in the time available. Use the net time.
- Mixing time units. Use one unit throughout.
- Applying Little's law to a system that is not steady. It needs long-term averages.
What next
Use this often? Add Cycle Time to your Home screen.
Frequently asked questions
What is a cycle time calculator?
A tool that finds the time per unit of a process, the takt time that demand needs, and the link between work in process, throughput and lead time.
What is takt time?
Takt time = net time available ÷ customer demand. Four hundred minutes for 400 units gives one minute per unit.
What is Little's law?
L = λ W: the average number in a system equals the arrival rate times the average time in the system.
What is the difference between takt time and cycle time?
Takt time is the pace the customer needs. Cycle time is the pace the process delivers.
How do I find the lead time from work in process?
W = L ÷ λ, the work in process divided by the throughput.